ISTQB Certified Tester: Foundation Level - Exam Paper 02

Image
1.Software testing activities should start a. as soon as the code is written b. during the design stage c. when the requirements have been formally documented d. as soon as possible in the development life cycle 2.Faults found by users are due to: a. Poor quality software b. Poor software and poor testing c. bad luck d. insufficient time for testing 3.What is the main reason for testing software before releasing it? a. to show that system will work after release b. to decide when the software is of sufficient quality to release c. to find as many bugs as possible before release d. to give information for a risk based decision about release 4. which of the following statements is not true a. performance testing can be done during unit testing as well as during the testing of whole system b. The acceptance test does not necessarily include a regression test c. Verification activities should not involve testers (reviews, inspections etc) d. Test environments shou

ISTQB Certified Tester: Foundation Level - Exam Paper 01

Image
1 When what is visible to end-users is a deviation from the specific or expected behavior, this is called: a) an error b) a fault c) a failure d) a defect e) a mistake 2 Regression testing should be performed: v) every week w) after the software has changed x) as often as possible y) when the environment has changed z) when the project manager says a) v & w are true, x – z are false b) w, x & y are true, v & z are false c) w & y are true, v, x & z are false d) w is true, v, x y and z are false e) all of the above are true 3 IEEE 829 test plan documentation standard contains all of the following except: a) test items b) test deliverable c) test tasks d) test environment e) test specification 4 Testing should be stopped when: a) all the planned tests have been run b) time has run out c) all faults have been fixed correctly d) both a) and c) e) it depends on the risks for the system being tested 5 Order numbers on a stock control sys

What are the roles and responsibilities of a Test Analyst?

Image
The very obvious responsibility of a software tester is to test the programs and report the bugs. During the test planning and preparation stages of testing, testers are to review and construct test plans along with analyzing and assessing the requirements of the design. The responsibilities differ depending on the firms that one is associated with. For example, smaller companies are able to hire lesser people and hence an individual employed in such a company has to tackle much more responsibilities than the employees of a bigger company. Apart from their obvious functions, software testers are given additional responsibilities depending on the companies they work for. Some of these add-ons include: • To point out the errors made during the development of the program • To make sure of a certain quality standard of the software • To increase the customer’s confidence on as well as their satisfaction from the program • To ensure that the application does not result in a fai